Updated on Tuesday, 21-Nov-2006 15:08:10 CET
|
|
+ = in progress
|
|
X = finished
|
|
Numbering Scheme
|
|
|
|
Coil
|
| Cavern Position (Sector)
| S14
| S12
| S4
| S10
| S16
| S8
| S2
| S6
|
| Coil
| B1
| B2
| B3
| B4
| B5
| B6
| B7
| B8
|
| Magnet Type
| X+
| X-
| X+
| X-
| X+
| X-
| X+
| X-
|
| Cold Mass
| CM1
| CM2
| CM3
| CM4
| CM5
| CM6
| CM7
| CM8
|
| Coil Casing
| CC1
| CC2
| CC5
| CC4
| CC8
| CC6
| CC7
| CC3
|
| Double Pancake (side A)
| DPC05
| DPC09
| DPC03
| DPC01
| DPC15
| DPC07
| DPC13
| DPC11
|
| Double Pancake (side B)
| DPC06
| DPC10
| DPC04
| DPC02
| DPC16
| DPC08
| DPC14
| DPC12
|
| Vacuum Vessel
| VV1
| VV8
| VV5
| VV6
| VV3
| VV4
| VV7
| VV2
|
|
|
|
|
|
|
|
|
|
|
|
Cold Mass Integration
|
|
| B1
| B2
| B3
| B4
| B5
| B6
| B7
| B8
|
Start Integration: August 2002
Finished Integration: October 2003
|
| Double Pancake A
| X
| X
| X
| X
| X
| X
| X
| X
|
| Turnover
| X
| X
| X
| X
| X
| X
| X
| X
|
| Double Pancake B
| X
| X
| X
| X
| X
| X
| X
| X
|
| Impregnation
| X
| X
| X
| X
| X
| X
| X
| X
|
|
|
|
Cryostat Integration
|
|
| B1
| B2
| B3
| B4
| B5
| B6
| B7
| B8
|
Start Integration: Summer 2003
Finished Integration: September 2005
|
|
Cold Mass
|
| Cooling Lines
| X
| X
| X
| X
| X
| X
| X
| X
|
| Conductor Bending
| X
| X
| X
| X
| X
| X
| X
| X
|
| Tie Rods
| X
| X
| X
| X
| X
| X
| X
| X
|
| Cryo-stops
| X
| X
| X
| X
| X
| X
| X
| X
|
| Instrumentation
| X
| X
| X
| X
| X
| X
| X
| X
|
| MLI
| X
| X
| X
| X
| X
| X
| X
| X
|
|
Thermal Shield
|
| Panels
| X
| X
| X
| X
| X
| X
| X
| X
|
| Cooling Lines
| X
| X
| X
| X
| X
| X
| X
| X
|
| Supports
| X
| X
| X
| X
| X
| X
| X
| X
|
| Instrumentation
| X
| X
| X
| X
| X
| X
| X
| X
|
| MLI
| X
| X
| X
| X
| X
| X
| X
| X
|
|
Vacuum Vessel
|
| Preparation VV
| X
| X
| X
| X
| X
| X
| X
| X
|
| Insertion
| X
| X
| X
| X
| X
| X
| X
| X
|
| Welding
| X
| X
| X
| X
| X
| X
| X
| X
|
|
|
|
Test Station
|
|
| B1
| B2
| B3
| B4
| B5
| B6
| B7
| B8
|
First Coil Tested: 7 September 2004
Last Coil Tested: 7 June 2005
|
| Installation
| X
| X
| X
| X
| X
| X
| X
| X
|
| Vacuum
| X
| X
| X
| X
| X
| X
| X
| X
|
| Cool Down
| X
| X
| X
| X
| X
| X
| X
| X
|
| Test
| X
| X
| X
| X
| X
| X
| X
| X
|
| Warm-up
| X
| X
| X
| X
| X
| X
| X
| X
|
|
|
|
Installation
|
|
| B1
| B2
| B3
| B4
| B5
| B6
| B7
| B8
|
First Coil in Position: 3 November 2004
Last Coil in Position: 25 August 2005
|
| Preparation
| X
| X
| X
| X
| X
| X
| X
| X
|
| Connection Boxes
| X
| X
| X
| X
| X
| X
| X
| X
|
| Transport to SX1
| X
| X
| X
| X
| X
| X
| X
| X
|
| VV Heaters
| X
| X
| X
| X
| X
| X
| X
| X
|
| Lowering into UX15
| X
| X
| X
| X
| X
| X
| X
| X
|
| Coil in Position
| X
| X
| X
| X
| X
| X
| X
| X
|
|
|
|
Warm Structure and Cryo-ring
|
| Cavern Position (Sector)
| S13
| S11
| S15
| S9
| S1
| S7
| S3
| S5
|
| Cryo-ring Segment
| C1
| C3
| C4
| C5
| C6
| C7
| C8
| C2
|
|
|
|
Installation
|
Release of support jacks: 29 September 2005
Cryo-ring Installation Finished: 20 March 2006
|
| Bed Plates & Feet
| X
|
|
| Struts and Voussoirs
| X
| X
| X
| X
| X
| X
| X
| X
|
| Shimming
| X
| X
| X
| X
| X
| X
| X
| X
|
| Valve Box
| X
|
|
| Cryo-ring
| X
| X
| X
| X
| X
| X
| X
| X
|
| Current Lead Cryostat
|
| X
|
|
|
|
Barrel Toroid
|
|
Test & Commissioning
|
| Vacuum
| 28 March 2006: start pumping & leak testing
|
| 19 May 2006: diffusion pumps in operation
|
| Cool Down
| 4 July 2006: start cooling
|
| 31 August 2006: reached 4 K (superconducting)
|
| Commissioning
| 17 October 2006: 1 kA
|
| 18 October 2006: 5 kA
|
|
9 November 2006:
21 kA (nominal current)
|
|
|